Question
PLease be as detailed as possible and answer all parts using relevant charts
Given the following problem and assume today's date is Jun. 30: Work Unit Completion Date Jan. 31 Feb. 28 Mar. 31 May 12 Jun. 30 Jul. 18 Aug. 30 Sep. 22 Oct. 29 Nov. 30 Budget (SM) Work Performed (SM) Actual Cost (SM) 10 12 15 13 12 20 20 30 35 1) 2) 3) 4) 5) 6) 7) 8) What is the Cost Variance? What is the Schedule Variance? What is the CPI? What is the SPI? What is the BAC? What is the ETC? What is the Percent Complete? What can be said about the status of this project?Explanation / Answer
BAC= $111M
ETC=$93M
Percent Complete= 38%
As on June 30th the project is more or less on schedule as heavier packages of the proejct are expected to go on air in August.
a b c d e f g h i j CV -2 1 -2 3 -10 - - - - - SV -2 -1 0 1 -10 - - - - - CPI 0.83 1 0.75 1.25 0.67 - - - - - SPI 1 0.8 1.33 0.87 1 - - - - -Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.