Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

PLease be as detailed as possible and answer all parts using relevant charts Giv

ID: 386950 • Letter: P

Question

PLease be as detailed as possible and answer all parts using relevant charts

Given the following problem and assume today's date is Jun. 30: Work Unit Completion Date Jan. 31 Feb. 28 Mar. 31 May 12 Jun. 30 Jul. 18 Aug. 30 Sep. 22 Oct. 29 Nov. 30 Budget (SM) Work Performed (SM) Actual Cost (SM) 10 12 15 13 12 20 20 30 35 1) 2) 3) 4) 5) 6) 7) 8) What is the Cost Variance? What is the Schedule Variance? What is the CPI? What is the SPI? What is the BAC? What is the ETC? What is the Percent Complete? What can be said about the status of this project?

Explanation / Answer

BAC= $111M

ETC=$93M

Percent Complete= 38%

As on June 30th the project is more or less on schedule as heavier packages of the proejct are expected to go on air in August.

a b c d e f g h i j CV -2 1 -2 3 -10 - - - - - SV -2 -1 0 1 -10 - - - - - CPI 0.83 1 0.75 1.25 0.67 - - - - - SPI 1 0.8 1.33 0.87 1 - - - - -
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote