Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

PLease be as detailed as possible and answer all parts using relevant charts Giv

ID: 387400 • Letter: P

Question

PLease be as detailed as possible and answer all parts using relevant charts Given the following problem and assume today's date is Jun. 30: Work Unit Completion Date Budget (SM) Work Performed (SM) Actual Cost (SM) Jan. 31 Feb. 28 Mar. 31 May 12 Jun. 30 Jul. 18 Aug. 30 Sep. 22 Oct. 29 Nov. 30 10 10 12 4 15 13 12 20 20 30 35 1) What is the Cost Variance? 2) What is the Schedule Variance? 3) What is the CPI? 4) What is the SPI? 5) What is the BAC? 6) What is the ETC? 7) What is the Percent Complete? 8) What can be said about the status of this project?

Explanation / Answer

1) Cost variance CV = Earned Value – Actual Cost = 55-67=-12 Negative value over budget

2) Schedule variance SV = EV – PV = 55-56=-1 Negative velue is small so bit over schedule

3) Cost performance index (CPI) = EV/AC=55/67 = 0.82=82%. Project is overbudget by 18%

4) Schedule performance index (SPI) = EV/PV = 55/56=0.98 less than 100% Schedule is on time with a value of 1 so the schedule is just slightly behind schedule at 98%.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote