A project manager is calculating budgetary reserves for the funding of a softwar
ID: 3919211 • Letter: A
Question
A project manager is calculating budgetary reserves for the funding of a software development project. In an attempt to develop cost models for security-related bugs, the manager determines a security-related bug is identified once every quarter and each bug costs roughly $20,000 to fix. Given project? the project is planned to last for two years, which of the following should the manager estimate for the cost of security-related bug remediation for the O A O B. ?jc O D $40,000 $80,000 $160,000 $320,000Explanation / Answer
This question comes under "Cost of quality" answer might be D "$320,000" because each bug a cost around 20,000 and for 8 quaters it might be $160,000 for 8 bugs.
But to stay on a safe side a manager should always think that bug count might be more than 8 (1 or more from each quater).
So answer is D "$320,000"
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.