I need a statement of work (SOW) based on the information below Project Overview
ID: 394935 • Letter: I
Question
I need a statement of work (SOW) based on the information below
Project Overview Below is the scenario for the course project assignment. You are assuming the role of the project manager for a company (you select the name) to provide a new product (Backpack with built in refrigerated pouch and radio module) to a customer (U.S. Army, Ground Forces and Special Operations). Scenario Your company was recently awarded a delivery contract on a new product (see below). You were newly hired by the company; you will assume the role as the assigned program manager overseeing the design, development, production and delivery of the new product. The details below provide a summary to the course project: Company type (name your company): A small defense contractor located in the United States of America Company size (employees): 100 Product: Backpack with built in refrigerated pouch and radio module Awarded quantity: 200 units (100 assigned to Ground Forces / 100 assigned to Special Operations) Program Budget: Proposed award: $1,500,000 Customer: U.S. Army, Ground Forces and Special Operations Award date: September 1, 2015 Completion date: March 1, 2017 Delivery schedule: 100 units 12mths ARO (after receipt of order). 50 units every 3 months after first delivery Milestone Schedule: First delivery: September 1 Second delivery: December 1 Last delivery: March 1 First milestone payment (from customer): October 30 Second Milestone payment: January 30 Final Milestone payment: May 30 Initial Program review (at the customer's site): November 16 Subsequent Program reviews: 6 months after the initial review Expected Result from Senior Management: On-time delivery for the three stated product deliverables Desire to complete the total program under the stated budget of $1,500,000 All milestones accomplished by due dates listed Supplemental (follow-on) contract for future additional units (backpacks
Explanation / Answer
Efficient Solutions Private Limited Statement of work
PROJECT SUMMARY
Efficient Solutions private limited is a manufacturer of high end backpacks with built in refrigerated storage and radio modules. It seeks to the same to the United States Army, Ground Forces and Special Operations.
SCOPE OF WORK
The scope of work includes designing, development/production and delivery of the backpacks. Specific deliverables and milestones will be listed in further mentioned sections .
PERIOD OF PERFORMANCE
The period of performance for Efficient Solutions Pvt. Ltd. is from September 1, 2015 to March 1, 2017 . All work must be scheduled to complete within this timeframe. Any modifications or extensions will be requested through advisers from US Army Utilities Departmnet for review and discussion.
PLACE OF PERFORMANCE
The manufcturing of the backpacks would be performed in the own facility of Efficient Solutions Private Limited.
WORK REQUIREMENTS
Efficient solutions private limited would perform the following tasks :
DESIGNING-
DEVELOPMENT / MANUFACTURING-
DELIVERY-
QUANTITY AND BUDGET
The contract is for 200 units (100 assigned to Ground Forces / 100 assigned to Special Operations) Program Budget is proposed at $1,500,000 .
SCHEDULE/MILESTONES
The below list consists of the initial milestones as identified by Efficient Solutions Pvt. Ltd.
First delivery: September 1
Second delivery: December 1
Last delivery: March 1
First milestone payment (from customer): October 30
Second Milestone payment: January 30
Final Milestone payment: May 30
Initial Program review (at the customer's site): November 16
Subsequent Program reviews: 6 months after the initial review
ACCEPTANCE CRITERIA
For efficient Solutions Pvt. Ltd. the acceptance of all deliverables is to performed by the VP of the Utilities Division of the United States Army. The VP of the Utilities Division of the United States Army willl maintain a team of four advisors who would evaluate each project phase as mentioned in work requirements and would approve the same for shifting to the next phase.
Once all project tasks have completed, a project closure and checklist with the VP of the Utilities Division of the United States Army and an acceptance would be requested showing acceptance of all deliverables and that efficient solutions pvt ltd. has compleated all the alloted tasks.