Lamda Computer Products competed for and won a contract to produce tow prototype
ID: 402510 • Letter: L
Question
Lamda Computer Products competed for and won a contract to produce tow prototype units of a new type of computer that is based on laser optics rater than on electronic binary bits. The first unit produced by Lamda took 5,000 hours to produce and required $250,000 worth of material, equipment usage and supplies. The second unit took 3,500 hours and used $200,000 worth of materials, equipment usage and supplies. Labor is $30 per hour.
a. Lamda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start
immediately. What would this bid be?
b. Supposed there was a significant delag between the contracts. During this time, personnel and equipment were reassigned to
other projects. Explain how this affect the subsequent bid?
Explanation / Answer
time for a single piece = 3500 hrs
time for 10 peices= 35000 hrs
cost of labor = 35000x30= 1,050,000 $
cost of materials= 200,000x10= 2,000,000$
so she sshould bid more than 3,050,000$