Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 1 1. The best source of revenue for a customer-requested scope change i

ID: 403063 • Letter: Q

Question

Question 1

1.       

The best source of revenue for a customer-requested scope change is:

Answer

A customer-funded contract amendment

Management reserve

Undistributed budget

Profits

Question 2

1.       

Earned value measurement systems must be capable of:

Answer

Measuring resources consumed

Measuring status and accomplishment

Provide a basis for diagnosis and replanning

All of the above

Question 3

1.       

At project initiation:

Answer

Few cost reduction opportunities exist and the cost of each change is large

Few cost reduction opportunities exist and the cost of each change is low

Many cost reduction opportunities exist and the cost of each change is high

Many cost reduction opportunities exist and the cost of each change is low

Question 4

1.       

A common cause for a favorable SV but unfavorable CV might be:

Answer

Using lower salaried workers

Using overtime

Using less expensive raw materials

All of the above

Question 5

1.       

The 50-50 rule is a technique used to determine:

Answer

EV

EAC

CPI

VAC

Question 6

1.       

A common cause for a favorable CV but unfavorable SV might be:

Answer

Too many workers on the project

Too few workers on the project

Crashing the project

Use of overtime

Question 7

1.       

Work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support, is called:

Answer

Measurable effort

Level of effort

Discrete estimates

Work package effort

Question 8

1.       

The weakness in all of earned value measurement is the way we calculate:

Answer

PV

EV

AC

EAC

Question 9

1.       

An S-Curve plots:

Answer

Cumulative cost as a function of time

Schedule variance as a function of time

Work package schedules as a function of time

None of the above

Question 10

1.       

Variance envelopes are usually established because:

Answer

All cost variances must be accounted for and explained

Not all cost variances must be explained even though they exist

All schedule variances must be explained

All cost overruns require sponsor authorization

Question 11

1.       

Which of the following is a human error/failure that can lead to tradeoffs?

Answer

Impossible schedule commitments

Poor control of design changes

Failure to receive approvals in a timely manner

All of the above

Question 12

1.       

Which of the following is normally NOT one of the three parameters considered during tradeoffs?

Answer

Time

Cost

Performance

Financial risks

Question 13

Which of the following generally gets reduced during tradeoffs?

Answer

Time

Cost

Performance

Financial risks

Question 14

1.       

With which of the following types of contracts will time be the first to be sacrificed?

Answer

Cost Contract

Fixed-Price-Incentive-Fee (FPIF)

Firm-Fixed-Price (FFP)

Cost Sharing

Question 15

1.       

The type of contract:

Answer

Can influence the order of tradeoffs

Never influences the order of tradeoffs

Is always subject to the Triple Constraint, that is, the relationship of the three project baselines - Schedule, Cost, and Quality or performance specifications

Has no bearing on the order of tradeoffs

Question 16

1.       

With which of the following types of contracts will cost be the first to be sacrificed?

Answer

Question 17

1.       

Which of the following are unexpected problems that can lead to tradeoffs?

Answer

Labor contract disputes

Old standards having been developed

Undercommitted company resources

Material shipments on time

Question 18

1.       

Cost and schedule overruns are generally caused by:

Answer

Scope changes

Replacement of the project manager midway through the project

Excessive turnover in the project team

Circumstances beyond the control of the project team

Question 19

1.       

Generally, in a non-profit organization, ________ is the first resource that will be compromised.

Answer

time

staff

performance

cost

Question 20

1.       

The first step in any decision-making process must be:

Answer

analyzing the project environment and status.

recognition and understanding of the conflict.

reviewing the project objectives.

revising the project plan.

Explanation / Answer

1.   

The best source of revenue for a customer-requested scope change is:

Answer

A customer-funded contract amendment


Question 2

1.   

Earned value measurement systems must be capable of:

Answer

All of the above


Question 3

1.   

At project initiation:

Answer

Many cost reduction opportunities exist and the cost of each change is low


Question 4

1.   

A common cause for a favorable SV but unfavorable CV might be:

Answer

Using overtime


Question 5

1.   

The 50-50 rule is a technique used to determine:

Answer

EV


Question 6

1.   

A common cause for a favorable CV but unfavorable SV might be:

Answer

Too few workers on the project


Question 7

1.   

Work that does not lend itself to subdivision into discrete scheduled increments of work, such as project support, is called:

Answer

Work package effort


Question 8

1.   

The weakness in all of earned value measurement is the way we calculate:

Answer

EV


Question 9

1.   

An S-Curve plots:

Answer

Cumulative cost as a function of time


Question 10

1.   

Variance envelopes are usually established because:

Answer

All cost variances must be accounted for and explained


Question 11

1.   

Which of the following is a human error/failure that can lead to tradeoffs?

Answer

All of the above


Question 12

1.   

Which of the following is normally NOT one of the three parameters considered during tradeoffs?

Answer

Performance


Question 13

Which of the following generally gets reduced during tradeoffs?

Answer

Cost


Question 14

1.   

With which of the following types of contracts will time be the first to be sacrificed?

Answer

Cost Contract


Question 15

1.   

The type of contract:

Answer

Can influence the order of tradeoffs


Question 16

1.   

With which of the following types of contracts will cost be the first to be sacrificed?

Answer

Cost Sharing


Question 17

1.   

Which of the following are unexpected problems that can lead to tradeoffs?

Answer

Labor contract disputes


Question 18

1.   

Cost and schedule overruns are generally caused by:

Answer

Scope changes


Question 19

1.   

Generally, in a non-profit organization, ________ is the first resource that will be compromised.

Answer

cost


Question 20

1.   

The first step in any decision-making process must be:

Answer

analyzing the project environment and status.


Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote