A time study analyst observes a worker over a period of time and calculates that
ID: 415877 • Letter: A
Question
A time study analyst observes a worker over a period of time and calculates that the worker required 30.0 minutes per unit produced. The worker was rated by the analyst at a 120 percent performance rating, and a 10 percent allowance for personal time and fatigue applies. (1) What is the standard time for this task? (2) If a worker managed to produce 16 units in an eight-hour day, what would their day's pay be if the base rate is $14 per hour, and the premium payment system paid on a 100 percent basis?
Explanation / Answer
1. Given the performance rating was 130% when a worker produces 1 unit in 30 min. Hence at 100% efficiency 1 unit will require 39 min (130*30/100) to complete 1 unit. Hence std time is 39 min.
2. AT 100% efficiency 1 unit requires 39 min. hence 16 unit will need 16*39= 624 min= 10.4 hr. Hence the pay at $14 per hour will be 10.4*14= $145.6.
This worker is working at an efficiency of 130% ((10.4-8)/8)
The amount of $145.6 is equivalent to the worker working at 130% efficiency for 8 hrs.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.