Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

QUESTION 5 often included in a You have asked your team to spend three weeks cre

ID: 421042 • Letter: Q

Question

QUESTION 5 often included in a You have asked your team to spend three weeks creating detailed descriptions of work package. Detailed descriptions of work packages are O A Project scope statement O B Work Breakdown Structure O C. WBS Dictionary O D Requirements traceability matrix QUESTION 6 Of the following methods of estimating, the least accurate is usually O A Parametric estimating O B. Analogous estimating O C. Bottom-up estimating O D. Top-down estimating QUESTION 7 When collecting requirements, which of the following group creativity techniques could be useful? OA Voting to obtain a majorthy O B. Questionnaires and surveys O C. Brainstorming O D. Prototypes QUESTION Significant points or events in the project are defined as O A Work packages O B. Tasks O C Activities O D. Milestones

Explanation / Answer

5. The answer is given below:

B. Work breakdown structure

The cost of the project can be estimated through work breakdown structure, so that the completion time can be estimated through work package.

6. The answer is given below:

D. Top- down estimating

The least accurate method is top down estimating, as where the details and informations will not be there and that lead towards lack of accuracy.

7. The answer is given below:

C. Brainstorming

Through a team creativity techniques, solution for the problem can be provided with brainstorming activities, as where new ideas can be developed.

8. The answer is given below:

D. Milestones

Milestone is said to be event or significant point, as where the project is ready to be delivered, as that determines the completion phase of the project.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote