Given the information? below, estimate the probability that the noncritical path

ID: 422165 • Letter: G

Question

Given the information? below, estimate the probability that the noncritical path

B-F-Gwill take more than 20weeks. ?Hint: Subtract from 1.0 the probability that

B-F-Gwill take 20weeks or less. Refer to the standard normal table

????????????????????????????????????????????????????????????????????????????????????????????????????  

Activity

Expected Time? (weeks)

Variance

A

4.04.0

1.00

B

5.05.0

0.96

C

3.53.5

0.25

D

11.511.5

2.07

E

6.06.0

2.10

F

9.09.0

2.55

G

5.05.0

0.49

The probability that this path will take more than 20weeks to complete is _.  

(Enter your response rounded to four decimal places.?)

Activity

Expected Time? (weeks)

Variance

A

4.04.0

1.00

B

5.05.0

0.96

C

3.53.5

0.25

D

11.511.5

2.07

E

6.06.0

2.10

F

9.09.0

2.55

G

5.05.0

0.49

Explanation / Answer

total duration of path

B-F-G =5+9+5=19 weeks

expected time TE=19

variance

0.96+2.55+0.49=4

standard deviation s = sqrt(variance)=2

z=(TS-TE)/ s = ( 20-19)/2 =0.5

from table of z score

at z=0.5

P=0.3085

so the answer is Probability =0.3085