Uhura Enterprises provides consulting services for customers. Consultants are brought in for two-hour shifts. A consultant will spend one full hour with a customer. The customers remain for that hour and then leave. Each consultant is paid $25 per hour. Let Xi represent the number of consultants starting their shift at hour i, (i = 1,2,3,4). The firm wishes to minimize salary costs while satisfying demand. Customer demand is as follows.
1:00-2:00 4
2:00-3:00 5
3:00-4:00 10
4:00-5:00 4
5:00-6:00 8
What is the proper objective function?
A.) Min 4X1 + 5X2 + 10X3 + 4X4
B.) Min 9X1 + 15X2 + 14X3 + 12X4
C.) Max 9X1 + 15X2 + 14X3 + 12X4
D.) Max 25X1 + 25X2 + 25X3 + 25X4
E.) Min 50X1 + 50X2 + 50X3 + 50X4
Explanation / Answer
Answer: - Option "E"------ Min 50X1+50X2+50X3+50X4
Explanation: - Given data
Consultants working for 2 hour shift
Each consultant is paid with $25 for each hour
It mean for 2 hours total cost is = 2 * $25 = $50
From the given data Xi Represents the no.of consultants starting their shift where i =1,2,3,4
Where it represent X1, X2, X3 ,X4 consultants
Cost Constraint to minimize salary cost = $50
The minimize function = Min 50X1+50X2+50X3+50X4