An accountant wishes to predict direct labor cost (y) on the basis of the batch

ID: 426302 • Letter: A

Question

An accountant wishes to predict direct labor cost (y) on the basis of the batch size (x) of a product produced in a job shop. Data for 12 production runs are given in the table below, along with the Excel output from fitting a least squares regression line to the data Direct Labor y ($1 71 663 381 138 861 145 493 548 251 1024 435 772 Batch 35 12 83 14 46 52 23 100 41 75 BClickherefortheExcelData File Batch Size Line Fit Plot 1000 + LaborCost 18.488+ 10.146 BSize 800 600 8 400 -200 0 100 Batch Stze

Explanation / Answer

Part a.

correct

Part b.

the coefficent, b0 represent y-axis intercept when x = 0, thus the b0 is the estimated mean labor cost when batch size is eual to zero. The coefficent b1 represent slope of line, that is increase in y value with unit increae in x value. Thus, b1 = 10.146 means, y increases by 10.146 units when x increased by 1 unit.

part b: mean labor cost, batch size, yes

increase, main labor cost, batch size

Part c: equation is given as : y = b0 + b1x

y = 18.488 + 10.146x

part d:

substitute x = 60 in equation, the y value is obtained as follows:

y = 18.488 + 10.146x = 18.488 + 10.146(60)

y = 627.26