Project Managment

Which best describes the NPV of a project?

The future monetary value of a project

The order in which projects should be undertaken

The present value of a projects future cashflows

The present value of a project's future cashflows, less the initial cost of the project

The value of a project, minus the value of other alternative projects.

A.

The future monetary value of a project

B.

The order in which projects should be undertaken

C.

The present value of a projects future cashflows

D.

The present value of a project's future cashflows, less the initial cost of the project

E.

The value of a project, minus the value of other alternative projects.

Explanation / Answer

Net present value (NPV) is used to determine the current value of all future cash flows generated by a project after deducting the initial capital investment. Hence the correct option is d. The present value of a project's future cashflows, less the initial cost of the project