Multiple Choice: Select single best answer. 1. You are new to a project that has been underway for some time. One of your first jobs as project manager is to familiarize yourself with, and understand, the scope baseline. What documents make up the scope baseline? a. The WBS, the project management plan, and the change register b. The project scope statement, the WBS, and the WBS dictionary c. The WBS, the change register, and the project scope statement d. The project scope statement, the WBS, and the risk register 2. Which of the following BEST describes when a project baseline should be changed? a. When a major delay occurs b. When an approved change is made c. When a cost increase occurs d. Changes should never be made to the baseline 3. A project is plagued by changes to the project charter. Who has the primary responsibility to decide if these changes are necessary? a. The stakeholders b. The project manager c. The project team d. The sponsorExplanation / Answer
1. A. The WBS, the project management plan, and the change register.
2. B. When an approved change is made BEST describes when a project baseline should be changed.
3. D. The Sponsor has the primary responsibility to decide if these changes are necessary.
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.