An integrated electronic-chip manufacturer has a demand for a specific component

ID: 432792 • Letter: A

Question

An integrated electronic-chip manufacturer has a demand for a specific component of 800 parts per 8-hour day. The manufacturer wants to design a lean system using containers. The containers the manufacturer used for this component held 20 parts. It takes about 4 hours to round-trip a container from one work center to the next and back again. The manufacturer also wants to hold 10% of safety stock of this part in its system.

If the required safety stock was changed to zero, how many containers should the lean system be using, all else being constant?

5

Explanation / Answer

Answer:

Explanation:

Note: Please rate the answer.