Complete the network diagram, do the necessary calculations, and state the criti
ID: 436880 • Letter: C
Question
Complete the network diagram, do the necessary calculations, and state the critical path(s) and the project completion time. State the critical path(s) and the completion time as, for example, "A - B - C @ 20", meaning Activities A, B, and C comprise the critical path and the completion time is 20 time units.
Problem 2:
Activity IP time
A -- 3
B A 4
C A 4
D B 5
E B 2
F C,D 3
G E 4
H F,G 5
Explanation / Answer
Critical path A-B-D-F-H @ 20