Complete the network diagram, do the necessary calculations, and state the criti

ID: 436880 • Letter: C

Question

Complete the network diagram, do the necessary calculations, and state the critical path(s) and the project completion time. State the critical path(s) and the completion time as, for example, "A - B - C @ 20", meaning Activities A, B, and C comprise the critical path and the completion time is 20 time units.

Problem 2:


Activity   IP      time
A            --         3
B             A         4
C             A         4
D             B         5
E             B         2
F            C,D       3
G            E          4
H            F,G       5

Explanation / Answer

Critical path A-B-D-F-H @ 20