Complete the network diagram, do the necessary calculations, and state the critical path(s) and the project completion time. In a reply to this Sakai message (no attachments, no Word docs, no QM documents, etc.), state the critical path(s) and the completion time as, for example, "A - B - C @ 20", meaning Activities A, B, and C comprise the critical path and the completion time is 20 time units.

Problem 1:
Activity    IP    time
A              --       2
B               A      3
C               A      4
D              B     4
E              C      4
F             D,E     5

Explanation / Answer

A-C-E-F @ 15