Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Consider a project whose activities are listed in the table below. Activity A wi

ID: 443762 • Letter: C

Question

Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…

Duration of A < Duration of B

Duration of A + Duration of C > Duration of B + Duration of D

Duration of A + Duration of C < Duration of B + Duration of D

Duration of A <= Duration of B + Duration of D

Consider a project whose activities are listed in the table below. In order to ensure that the project is completed on time, Activity B must start, at the latest, by time…

a. 0

b. 1

c. 2

d. 3

Activity Immediate Predecessors A none B none C A D B E C,D F E G E

Explanation / Answer

(1) Activity A will have slack time as long as Duration of A + Duration of C < Duration of B + Duration of D .

Critical path have zero slack.

(2) In order to ensure that the project is completed on time, Activity B must start, at the latest, by time 0 because B is the first activity on critical path.

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote