Consider a project whose activities are listed in the table below. Activity A wi
ID: 443762 • Letter: C
Question
Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…
Duration of A < Duration of B
Duration of A + Duration of C > Duration of B + Duration of D
Duration of A + Duration of C < Duration of B + Duration of D
Duration of A <= Duration of B + Duration of D
Consider a project whose activities are listed in the table below. In order to ensure that the project is completed on time, Activity B must start, at the latest, by time…
a. 0
b. 1
c. 2
d. 3
Activity Immediate Predecessors A none B none C A D B E C,D F E G EExplanation / Answer
(1) Activity A will have slack time as long as Duration of A + Duration of C < Duration of B + Duration of D .
Critical path have zero slack.
(2) In order to ensure that the project is completed on time, Activity B must start, at the latest, by time 0 because B is the first activity on critical path.