In an MRP table, the gross requirement in period 7 is 50 units. There are 15 uni

ID: 443929 • Letter: I

Question

In an MRP table, the gross requirement in period 7 is 50 units. There are 15 units on hand at the end of period 6, and no units are scheduled to be received in period 7. Lead time is 2 periods. Assuming lot for lot ordering, which of these would be the proper output of the MRP system?

Planned order receipt of 35 units in period 5

Planned order release of 35 units in period 5

Planned order receipt of 50 units in period 5

Planned order release of 50 units in period 5

1.

Planned order receipt of 35 units in period 5

2.

Planned order release of 35 units in period 5

3.

Planned order receipt of 50 units in period 5

4.

Planned order release of 50 units in period 5

Explanation / Answer

Answer will vary depending on the production plan and receipt schedule for period 5.

I believe there is more information that is available on the requirement for and material availability for period 5 atleast to solve the question. However I am giving the logic on how to solve this question for understanding. Please check and come back if more information is available. I will post the values accordingly

Assuming Opening for period 5 is 0

Period 5 Opening 0 A Purchase B Production C Closing D = A+B-C Period 6 Opening E = D Purchase F Production G Closing 15 H = E+F-G Period 7 Opening Balance 15 I=H Purchase 0 J Requirment 50 K