Razzle Dazzle Inc. was asked to produce 6 prototype disco lighting systems for a

ID: 446562 • Letter: R

Question

Razzle Dazzle Inc. was asked to produce 6 prototype disco lighting systems for a new “That’s 70’s” theme restaurant chain. The time to produce each of the systems is shown in the following table.

System

Time (Minutes)

1

46

2

39

3

35

4

33

5

32

6

30

Based on initial customer reaction, RD’s customer expects the T70’s chain to “go national” requiring a total of 200 systems to be delivered. How much time would you expect the 200th unit to take to produce?

System

Time (Minutes)

1

46

2

39

3

35

4

33

5

32

6

30

Explanation / Answer

Every 6 system takes 30. So 33 such(33*6= 198) cycles would mean 198 will also take 30 min.

so 200 will take 39 min.