Complete the MRP schedule for the product below. Product A Lot Size = 75 Safety

ID: 449967 • Letter: C

Question

Complete the MRP schedule for the product below.

Product A Lot Size = 75 Safety Stock = 50

Lead Time = 1 week Allocated = 100 In hand =300

WEEKS


     
1  
2     
3  
4  
5      

Gross requirement  
  
500  
700  
400  
500     

Scheduled receipt  
600                     

Available on-hand                           

Net requirements                         

Planned order receipts                         

Planned order releases                         

Product X has the structure given below.   
X
  

P3 R2 S2
  
  
Q4 T3 V2

Explanation / Answer

Summarized bill of material

Product

Quantity

A

3

B

2

C

2

D

4

E

3

F

2

Product

Quantity

A

3*100 = 300

B

2*100=200

C

2*100=200

D

4*100=400

E

3*100=300

F

2*100=200

Week

1

2

3

4

5

6

7

8

9

10

Gross Requirement

D (300)

F (200)

E (400)

B(200)

C (400)

A (100)

Schedule receipts

D (300)

F (200)

E (400)

B(200)

C (400)

A(100)

Net Requirement

D (300)

F (200)

E (400)

B (200)

C (400)

A (100)

Planned order release

A (100)

Product

Quantity

A

3

B

2

C

2

D

4

E

3

F

2