Complete the MRP schedule for the product below.
Product A Lot Size = 100 Safety Stock = 50
Lead Time = 1 week Allocated = 200 In hand =600
WEEKS
1
2
3
4
5
Gross requirement
200
500
300
800
400
Scheduled receipt
100
Available
Net requirements
Planned order receipts
Planned order releases
Explanation / Answer
Product A Lot Size = 100 Safety Stock = 50 Allocated = 200 WEEKS Lead Time = 1 week 0 1 2 3 4 5 Gross requirement 200 500 300 800 400 Scheduled receipts 100 0 0 0 0 Available/Projected On Hand 600 300 100 100 100 100 Net requirements 0 250 250 750 350 Planned order receipts 0 300 300 800 400 Planned order releases 0 300 300 800 400 0 Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement* Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed, Here 1 week before *Projected On Hand Calculation for first week = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement - Allocated
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.