What does diseconomies of scale mean? A. Adding more people to an already late p
ID: 451019 • Letter: W
Question
What does diseconomies of scale mean?
A. Adding more people to an already late project will make it later.
B. Adding people to a project that is on time will move the completion date ahead by 0.51%.
C. Adding people to a late project can accelerate the project to on time.
D. For every person added to a late project, the expected completion date moves up the scale of diseconomy by a factor of 1.325. E. For every day the project is late, the organization will suffer financial lose following this scale.
Explanation / Answer
D. For every person added to a late project, the expected completion date moves up the scale of diseconomy by a factor of 1.325.