Given a simple Project like the one pictured above. Optimistic / Most Likely / P
ID: 451248 • Letter: G
Question
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 33 and a Path Standard Deviation = 4. For Path 1-3-4-5 we have a Path Mean = 34 and a Path Standard Deviation = 3. Determine both the Probability that Path 1-2-5 will finish in 34 Days or Less and the Probability that the Project will finish in 34 Days or Less.
Question 5 options:
0.84134474 : 0.707860972?
0.77337272 : 0.578101934?
0.598706274 : 0.299353137?
0.987775567 : 0.983991966?
0.84134474 : 0.707860972?
0.77337272 : 0.578101934?
0.598706274 : 0.299353137?
0.987775567 : 0.983991966?
Explanation / Answer
In above case diagram is not visible .
I am just predicting from the given information.
For
1 - 2 - 5
Mean = 33
SD = 4
Probability that Path 1-2-5 will finish in 34 Days or Less
Z= T- Te / Sigma
= 34 - 33/4
=0.25
The value of 0.25 from Normal table is 0.098
Z = 0.5 + 0.098
=0.5987
-------------------------------------------------------------------------------------------------------------------------------------------------------------------
For Path 1-3-4-5
1-3-4-5
Mean = 34
SD = 3
Z= T- Te / Sigma
= 33 - 34/3
= - 0.33 Means 0.33
The value of Z for 0.33 is 0.20
Z = 0.5 - 0.200
=0.299353
So answer
0.598706274 : 0.299353137
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.