Given a simple Project like the one pictured above. Optimistic / Most Likely / P
ID: 434316 • Letter: G
Question
Given a simple Project like the one pictured above. Optimistic / Most Likely / Pessimist Times were assessed and Path Means and Path Standard Deviations were calculated. For Path 1-2-5 we have a Path Mean = 29 and a Path Standard Deviation = 3. For Path 1-3-4-5 we have a Path Mean = 32 and a Path Standard Deviation = 4. Determine both the Probability that Path 1-2-5 will finish in 32 Days or Less and the Probability that the Project will finish in 32 Days or Less.
Question 5 options:
0.977249938 : 0.755778443
2-
0.747507533 : 0.299970083
3-
0.990184693 : 0.833086683
4- 0.84134474 : 0.42067237
1-0.977249938 : 0.755778443
2-
0.747507533 : 0.299970083
3-
0.990184693 : 0.833086683
4- 0.84134474 : 0.42067237
Explanation / Answer
Correct Answer:
D
For path 1-2-5,
Z = (32-29)/3 = 1
At Z = 1, the area covered = .8413
For path 1-3-4-5,
Z = (32-32)/4 = 0
At Z = 0, the area covered = .50