1a. Master Production Scheduling: complete the following table safety Stock = 0

ID: 452092 • Letter: 1

Question

1a. Master Production Scheduling: complete the following table

safety Stock = 0

Master Production Schedule

Beginning Inventory =

60

weeks

1

2

3

4

5

6

7

8

Forecast Orders

15

15

15

15

15

15

15

15

Actual Orders

17

20

16

15

15

5

5

Projected Inventory

MPS

Available to Promise

Order quantity lots of 10

Order Lead time = 3 week

Just need some help with the table. Thanks!

safety Stock = 0

Master Production Schedule

Beginning Inventory =

60

weeks

1

2

3

4

5

6

7

8

Forecast Orders

15

15

15

15

15

15

15

15

Actual Orders

17

20

16

15

15

5

5

Projected Inventory

MPS

Available to Promise

Order quantity lots of 10

Order Lead time = 3 week

Just need some help with the table. Thanks!

Explanation / Answer

Safety Stock = 0 Lead Time - 3 weeks Beginning Inventory = 60 Lot Size 10 units 1 2 3 4 5 6 7 8 Forecast Orders 15 15 15 15 15 15 15 15 Actual Orders 17 20 16 15 15 5 5 0 Projected Inventory 53 33 17 12 7 2 7 2 MPS 10 10 10 20 10 0 0 0 ATP 23 -21 -20 0 0 0 0 0 Projected on-hand inventory For Period 1 = Beginning Inventory + MPS (3 week earlier) - Max of Forecast or Customer orders For Subsequent periods = Projected on-hand inventory + MPS (3 week earlier) - Max of Forecast or Customer orders * As Lead time 3 weeks Available to promise For Period 1 = Beginning Inventory + MPS - Customer Order for Current and Next periods For Subsequent periods = If MPS>0, MPS - Customer Order for subsequent two periods For MPS = 0, ATP = 0