Given the following information: Activity Duration 1-2 4 2-4 9 4-7 5 7-10 2 10-1
ID: 453298 • Letter: G
Question
Given the following information:
Activity
Duration
1-2
4
2-4
9
4-7
5
7-10
2
10-12
3
2-5
8
5-8
7
8-10
2
1-3
10
3-6
6
6-9
4
9-11
5
11-12
6
What is the ES (earliest start time) of activity 10-12? (Fill in only number, no unit.)
What is the LF (latest finish time) of activity 10-12? (Fill in only number, no unit.)
What is the LF of activity 1-2? (Fill in only number, no unit.)
What is the expected duration of this project? (Fill in only number, no unit.)
Activity
Duration
1-2
4
2-4
9
4-7
5
7-10
2
10-12
3
2-5
8
5-8
7
8-10
2
1-3
10
3-6
6
6-9
4
9-11
5
11-12
6
Explanation / Answer
The above questions can be answered by making a table for the given project data
Based on the above calculations,
ES of activity 10-12 is 22
LF of activity 10-12 is 31
LF of activity 1-2 is 4
Expected duration of the project is 31
Activity Duration ES LS EF LF 1-2 4 0 4 0 4 1-3 10 0 10 0 10 2-4 9 4 13 12 21 2-5 8 4 12 11 19 3-6 6 10 16 10 16 4-7 5 13 18 21 26 5-8 7 12 19 19 26 6-9 4 16 20 16 20 7-10 2 18 20 26 28 8-10 2 20 22 26 28 9-11 5 20 25 20 25 10-12 3 22 25 28 31 11-12 6 25 31 25 31Related Questions