Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 7.7. (TCO 3) The Identification step requires inputs such as (Points :

ID: 457831 • Letter: Q

Question

Question 7.7. (TCO 3) The Identification step requires inputs such as (Points : 5) WBS. RBS. a risk management plan. All of the above None of the above Question 8.8. (TCO 3) The output of the Identification step is (Points : 5) the probability-impact matrix. the project scope statement. risk categories. a list of described risks. None of the above Question 9.9. (TCO 3) The WBS does not address (Points : 5) organizing the work. the effort and duration of the work. resources. scheduling. the cost of the work.

Explanation / Answer

7.7. The correct answer is a risk management plan.

The inputs to identify risk are:-

1. Risk Management Plan
2. Activity Cost Estimates
3. Activity Duration Estimates
4. Scope Baseline
5. Stakeholder Register
6. Cost Management Plan
7. Schedule Management Plan
8. Quality Management Plan
9. Project Documents
10. Enterprise Environmental Factors
11. Organizational Process Assets

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote