Question 7 pts The cost performance index measures which of the following? BCWP

ID: 1765271 • Letter: Q

Question

Question 7 pts The cost performance index measures which of the following? BCWP ACWP BCWS BCWP The planned value achieve to date compared to that actually completed The fraction of deliverables completed per unit cost The cost incurred to date which maybe invoiced against the project Question 8 pts The budget at completion (BAC) measures which of the following? The original cost estimate for the entire project The current cost estimate for the entire project The original cost estimate for the entire project modified by the schedule performance index None of the above The critical index Question 9 pts The variance at completion is a measure of what? More than one of the above The fraction of the deliverables at risk of being late The absolute value of deliverables at risk of being late The difference between the original total cost estimate and the current total cost estimate The ratio of the original total cost estimate and the current total cost estimate

Explanation / Answer

Answer 7- BCWP/ACWP

Answer 8- The original cost estimatefor entire project

Answer 9- The difference between the original total cost estimate and the current total cost estimate

Answer 10- All of these

Answer 11- The work performed to date as measured by original budget

Answer 12- The CI usually creates less of an adjustment then does the either SPI or CPI indiviually