Question 7 pts The cost performance index measures which of the following? BCWP
ID: 1866912 • Letter: Q
Question
Question 7 pts The cost performance index measures which of the following? BCWP ACWP BCWS BCWP The planned value achieve to date compared to that actually completed The fraction of deliverables completed per unit cost The cost incurred to date which maybe invoiced against the project Question 8 pts The budget at completion (BAC) measures which of the following? The original cost estimate for the entire project The current cost estimate for the entire project The original cost estimate for the entire project modified by the schedule performance index None of the above The critical index Question 9 pts The variance at completion is a measure of what? More than one of the above The fraction of the deliverables at risk of being late The absolute value of deliverables at risk of being late The difference between the original total cost estimate and the current total cost estimate The ratio of the original total cost estimate and the current total cost estimateExplanation / Answer
Answer 7- BCWP/ACWP
Answer 8- The original cost estimatefor entire project
Answer 9- The difference between the original total cost estimate and the current total cost estimate
Answer 10- All of these
Answer 11- The work performed to date as measured by original budget
Answer 12- The CI usually creates less of an adjustment then does the either SPI or CPI indiviually
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.