Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

12–27 A project manager discovers that his team has neglected to complete the ne

ID: 458687 • Letter: 1

Question

12–27 A project manager discovers that his team has neglected to complete the network diagram for the project. The network diagram is shown in Figure P12–27. However, the project manager has some information available, specifically that each activity, labeled A–G, has a different duration between one and seven weeks. Also, the slack time for each of the activities is known as shown in Figure P12–27 in ascending order.

Duration (weeks): 1, 2, 3, 4, 5, 6, 7

Slack time (weeks): 0, 0, 0, 2, 4, 4, 7

Using the clues provided below, determine the duration of each activity as well as the early start, early finish, latest start and latest finish times for each activity.

Clues

1.Activity E is on the critical path.

2.The early start (ES) time for activity F is five weeks.

3.The duration of activity B is seven weeks.

4.Activity D has four weeks of slack, but activity F has a greatest amount of slack.

5.The early finish (EF) time for activity G is seventeen weeks.

6.The latest finish (LF) time for activity E is thirteen weeks.

Activity     Duration      Early Start        Early Finish       Latest Start       Latest Finish

A             ________     _________       __________      __________      _________

B             ________     _________       __________      __________      _________

C             ________     _________       __________      __________      _________

D             ________     _________       __________      __________      _________

E             ________     _________       __________      __________      _________

F             ________     _________       __________      __________      _________

G             ________     _________       __________      __________      _________

Explanation / Answer

Activity Duration ES EF LS LF Slack A 3 0 3 4 7 4 B 7 0 7 0 7 0 C 5 0 5 2 7 2 D 2 7 9 11 13 4 E 6 7 13 7 13 0 F 1 5 6 12 13 7 G 4 13 17 13 17 0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote