At a make-to-order hamburger shop, there is one worker who grills patties, two w
ID: 458994 • Letter: A
Question
At a make-to-order hamburger shop, there is one worker who grills patties, two workers who assemble burgers, and one cashier. Their grill can grill patties in 4 minutes and the grill can cook up to 20 patties at one time. Each burger assembler can assemble a burger in 40 seconds. It takes the cashier 6 seconds to collect payment. What is the capacity of the hamburger restaurant in customers per minute? What is the bottleneck? Assume on burger per customer. If two more burger assemblers are hired, what is the capacity of the burger store? What is the bottleneck? Disregarding part b, if the restaurant buys another grill, what is the capacity of the restaurant? What is the bottleneck? (Assume the one griller can use both grills.)Explanation / Answer
a) Grill can cook 20 patties in 4 minute
Time to assemble each burger = 40 seconds
Time taken by cashier = 6 seconds
Total time taken by one burger = 4 minute + 40 seconds + 6 seconds
Time taken to serve 20 burgers = 240 seconds + 400 seconds (20 burger and 2 worker) + 120 seconds (20 burger)
= 760 seconds
In this case, second round of burger preparation cannot be started because 480 seconds (second reound ) + 40 seconds is less than last burger preparation in first round.
thus capacity of hamburger restaurant= 20 * 60/760
=1.5 customer/minute i.e 1 customer/minute
Bottleneck is burger assemblers
b)
Time taken to serve 20 burgers = 240 seconds + 200seconds (20 burger and 2 worker) + 120 seconds (20 burger)
= 560 seconds
thus capacity of hamburger restaurant= 20 * 60/560
= 2 customer/minute
Bottleneck= Grill
c)
Time taken to serve 40 burgers = 240 seconds + 800 seconds (20 burger and 2 worker) + 240 seconds (20 burger)
= 1280 seconds
thus capacity of hamburger restaurant= 40 * 60/1280
= 1.875 customer/minute i.e 1 customer/minute
Bottle neck= burger assemblers