QUESTION 11 It is important to maintain the daily construction diary because: It
ID: 460795 • Letter: Q
Question
QUESTION 11
It is important to maintain the daily construction diary because:
It can be used in assessing the competency of the inspector.
It is a legal document.
It records all events that happened on-site.
It is a reflection of the project success.
QUESTION 12
In general, the average shrinkage of volume of surface soil is about:
18%
10%
12%
15%
QUESTION 13
As a result of research conducted by the Associated General Contractors of America, every type of soil is susceptible to cave-ins.
True
False
QUESTION 14
It is the responsibility of the _______________ to correct any problem that could happen at the mix plant.
Plant foreman
Inspector
Project engineer
Subcontractor
QUESTION 15
Computer record keeping (electronic storage) should not be used to keep a construction diary.
True
False
QUESTION 16
If a state elects to upgrade its safety code to meet the OSHA requirements, it has ___ years to do so.
2
3
4
5
QUESTION 17
Before the start of the paving process, the inspector duties involve:
Securing inspection tools
Inspection of paving equipment
Coordinate traffic control
All of the above
QUESTION 18
Under OSHA's requirements, periodic on-site inspections, including follow-up procedures, should be conducted by the PCM or design-build/turnkey contractor.
True
False
QUESTION 19
Mobilization costs are typically paid at the beginning of a project.
True
False
QUESTION 20
In situations where it is difficult to quantify the amount of work needed, a _________________ type of contract is recommended.
Lump-sum
Fixed-price
Unit-price
Time and Material
Explanation / Answer
11. It is a reflection of the project success.
Daily construction diary are used to document all the business activity happened every day thus play an important part in measuring the extent of project completion and its success
12. 15%
Shrinkage of volume of surface soil
13. True
According to the research, it has been found that no part of the country is immune from cave-in though majority of cave-ins are in shallow excavations.
14. Project Engineer
It is the responsibility of project engineer to correct any problem happen at mix plant as he is the one who is responsible for smooth operation of business activities.
15. False
Construction dairy can be kept in electronic mode. There are so many tools and application which are available in market for effective documentation of daily construction activities
16. 3 years
It is a general organization standard which is recommended by standard bodies.
17. All of the above
Inspector secure the inspection tools, coordinate traffic control and inspect the paving equipment in order to ensure the successful completion of paving process.
18. True
Periodic on-site inspection should be conducted by PCM or turnkey contractor as they are the one who is responsible for the implementation of quality process at site.
19. True
It is the payment that one requires from the customer at the starting of the project so that he can manage the initial activity and get ready with required resources.
20. Lump-sum
Because there is no clarity about the amount of work thus price will be paid on lump-sum basis for the job performed