You are the project manager for your company, Mark Manufacturers. Your company h

ID: 462072 • Letter: Y

Question

You are the project manager for your company, Mark Manufacturers. Your company has a large client that has requested a special component be created for one of their test engines. Your organization agrees and creates a standard contract with the customer, and your manager assigns you to manage this project. The project was launched because of which one of the following?

A.  A customer request

B.  A change in the technology your customer is creating

C.  A legal requirement (contractual)

D.  An organizational need

Explanation / Answer

A.  A customer request

Customer has requested for a special component ( apart from normal business). Thus it must be critical for the customer point of view, Thus a project is created to perform it on the stipulated time period and with more care and attention.