Tasya has to provide estimates for activities, but no one on the project team ha
ID: 472762 • Letter: T
Question
Tasya has to provide estimates for activities, but no one on the project team has performed them before. The project team is using a schedule from a similar project as the basis for its estimates. What type of estimating is this an example of? Select one: Budgetary Three-point estimate Parametric Analogous The actual cost for a previously budgeted procurement item is five percent more than expected. Where would this extra cost most likely be drawn from? Select one: Critical chain reserve Management reserve Contingency reserve Budget allowance Which one of the following is not an output of any of the processes in the Project Time Management knowledge area? Select one: Resource breakdown structure Project schedule network diagram Schedule model data Schedule management plan Work expands to fill the time available refers to which of the following? Select one: Monte Carlo Analysis Parkinson's Law Contingency reserve analysis Design of experimentsExplanation / Answer
Question 2:
D : ANALOGOUS ESTIMATING
Analogous estimating uses a similar past project to estimate the duration or cost of your current project, thus the root of the word: analogy.
Question 3:
C: Contingency reserve
Question 4:
A: Resoruce breadkwong structure
Question 5
B: Parkinson´s Law
This statement was made by Cyril Northcote Parkinson, the famous British historian
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.