Question 3 A Project consists of the following activities. Activities Times are

ID: 473205 • Letter: Q

Question

Question 3

A Project consists of the following activities. Activities Times are given in weeks.

Activity

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

A

--

13

16

19

B

A

21

37

33

C

A

5

7

15

D

A

7

9

13

E

B

24

28

32

F

B

15

18

25

G

C, F

19

21

27

H

D

24

28

32

I

H

5

9

18

J

G, I

4

12

13

K

E, J

15

19

24


1. Use appropriate nodes and arrows to draw the network diagram. On the network diagram, label the activity time under each node.
2. Scan your network diagram in the .pdf file format.
3. Submit your assignment by uploading the file.

Activity

Immediate Predecessors

Optimistic

Most Likely

Pessimistic

A

--

13

16

19

B

A

21

37

33

C

A

5

7

15

D

A

7

9

13

E

B

24

28

32

F

B

15

18

25

G

C, F

19

21

27

H

D

24

28

32

I

H

5

9

18

J

G, I

4

12

13

K

E, J

15

19

24

Explanation / Answer

Question 3 A Project consists of the following activities. Activities Times are

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote