Question 3 A Project consists of the following activities. Activities Times are
ID: 473205 • Letter: Q
Question
Question 3
A Project consists of the following activities. Activities Times are given in weeks.
Activity
Immediate Predecessors
Optimistic
Most Likely
Pessimistic
A
--
13
16
19
B
A
21
37
33
C
A
5
7
15
D
A
7
9
13
E
B
24
28
32
F
B
15
18
25
G
C, F
19
21
27
H
D
24
28
32
I
H
5
9
18
J
G, I
4
12
13
K
E, J
15
19
24
1. Use appropriate nodes and arrows to draw the network diagram. On the network diagram, label the activity time under each node.
2. Scan your network diagram in the .pdf file format.
3. Submit your assignment by uploading the file.
Activity
Immediate Predecessors
Optimistic
Most Likely
Pessimistic
A
--
13
16
19
B
A
21
37
33
C
A
5
7
15
D
A
7
9
13
E
B
24
28
32
F
B
15
18
25
G
C, F
19
21
27
H
D
24
28
32
I
H
5
9
18
J
G, I
4
12
13
K
E, J
15
19
24
Explanation / Answer
Question 3 A Project consists of the following activities. Activities Times are
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.