Question 1 1 pts The economic estimates for two cranes are shown in the table be
ID: 1131531 • Letter: Q
Question
Question 1 1 pts The economic estimates for two cranes are shown in the table below. The study period is nine years. For the case of alternative A, you would have to lease a crane for the final three years. Annual leasing costs will be $66.000 per year (plus the annual expenses of $28.800 per yearl The MARRIS 15% per year, hat is the incremental ERR (delta ERR) for both alternatives? Which alternative should be selected? (Hint: You must purchase a crane, do nothing is not an option) A. Capital investment $272,000 $346,000 Annual expenses 28,800 19,300 Useful life (vears)6 Market value (end of 25,00040,000 useful life) 19.9%, A 19.9%, 15.65% A 15.65%, B O NeitherExplanation / Answer
A
B
Incremental
Cash Flow of A-B
Capital Investment
272000
346000
-74000
Annual Expenses
1
28800
19300
9500
2
28800
19300
9500
3
28800
19300
9500
4
28800
19300
9500
5
28800
19300
9500
6
28800
19300
9500
7
28800+66000=94800
19300
75500
8
28800+66000=94800
19300
75500
9
28800+66000=94800
19300
75500
Salvage Value
25000
40000
-15000
MARR = 15%
Study Period = 9 years
What is the ERR?
Present Worth of outflows = -74000 – 15,000 (P/F, 15%, 9)
Present Worth of outflows = -74000 – 15,000 (.2843) = -78264 (Take 78264)
FW of outflows = 9500 (F/A, 15%, 6) (F/P, 15%, 3) + 75500 (F/A, 15%, 3)
FW of outflows = 9500 (8.754) (1.521) + 75500 (3.473) = 388702
78264 (1+i) 9 = 388702
(1+i) 9 = 388702 ÷ 78264
(1+i) 9 = 4.96 (take 5)
(1+i) = 1.1958
I = 1 – 1.1958
I = .1958 or 19.58%
ERR (19.58%) > MARR – Select Alternative A
Answer is close to Option A – 19.9%, Alternative A
A
B
Incremental
Cash Flow of A-B
Capital Investment
272000
346000
-74000
Annual Expenses
1
28800
19300
9500
2
28800
19300
9500
3
28800
19300
9500
4
28800
19300
9500
5
28800
19300
9500
6
28800
19300
9500
7
28800+66000=94800
19300
75500
8
28800+66000=94800
19300
75500
9
28800+66000=94800
19300
75500
Salvage Value
25000
40000
-15000
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.