As the project manager for a complicated bridge project, you have established the Critical Path that will dictate the project completion date. Of the following, which one would LEAST likely cause that critical path to change during the life of the project: a. Excavation for the footing exposed an ancient Native American burial ground. b. The project Owner agrees to provide incentive bonuses for early completion of critical tasks c. The Ironworkers union uses this project for apprentice training d. One of the labor unions goes on a month-long strike Highway maintenance forces utilize specialized equipment for maintenance operations. As discussed in class, name the equipment for the following operations: a. Mowing behind guiderail b. Clearing plugged culverts and pipes c. Drainage ditch cleaning and shaping d. Installing guiderail posts e. Cleaning catch basins

Explanation / Answer

The activity that would least likely cause to change the critical path is

c) The ironworkers union uses this project for apprentice training

Equipment for following operations are:

a) Mowing behind guiderail - Sickle Bar Mower & Under Guiderail mower

b) Clearing plugged culverts and pipes - Porta Mole underground boring machine
c) Drainage ditch cleaning and shaping - Excavator

d) Installing guiderail posts - Highway Guardrail Hydraulic Post Driver

e) Cleaning catch basins - Vacuum trucks

The most appropriate method for variable message sign message is (F)