NEED HELP SOLVING SETUP COSTS, the other two are correct,
my previous answers that are incorrect are 11,333 and 11,334. Please help. Will give THUMBS UP
Lakeside Inc. manufactures four lines of remote control boats and uses activity-based costing to calculate product cost. Estimated Total Cost Estimated Cost Driver Activity Cost Pools Machining Setup Quality control $ 325,000 13,200 machine hours 65,000 102,000 390 batches 800 inspections Suppose the Luxury boat requires 4,350 machine hours, 255 inspections, and 68 batches. Using activity proportions, determine the amount of overhead assigned to the Luxury product line. (Round your intermediate calculations to the nearest whole percentage and your final answer to the nearest whole number.) Cost Pool Allocated Overhead Machining Setup CostsS Quality Control$ Total Overhead $ 107,102 11,334 32,513 150,949Explanation / Answer
Cost Pool Allocated overhead Machining $ 107,102 =(325000/13200)*4350 Setup costs $ 11,333 =(65000/390)*68 Quality control $ 32,513 =(102000/800)*255 Total overhead $ 150,948 =107102+11333+32513
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.