5.1 S alem makes two products and expects to incur the following overhead costs
ID: 2337563 • Letter: 5
Question
5.1 S alem makes two products and expects to incur the following overhead costs next year: Machining Setup Packaging Total Overhead Costs $150,000 $70,000 $50,000 530,000 Salem expects the following next year: Prod Prod 2 Machining hours4,000 Number of setups Units Direct Labor Direct Materials 1,000 10 30 7,0003,000 $70,000 $30,000 $40,000 $50,000 a. What is the PDO assuming a single plant-wide rate based on direct labor cost? b. Using traditional method, how much overhead is assigned products 1? Product2? c. Using traditional method, what is the total cost of product 1? Product 2? d. If sales are $300,000 for prod 1 & $150,000 for product 2, what is the gross profit per unit using the single plant-wide rate? e. Use activity based costing to come up with ABC rates. f. Using ABC, how much overhead is assigned to product 1? Product 2? g. Using ABC, what is the total product cost of product 1? Product 2? h. If sales are $300,000 for prod 1 &$150,000 for prod 2, what is the gross profit per unit using ABC?Explanation / Answer
Answer a. Predetermined Overhead Rate = $150,000 (Total Overhead) / $100,000 (Direct Labor Cost) Predetermined Overhead Rate = 150% of Direct Labor Cost Answer b. Product 1 Product 2 Direct Labor 70,000.00 30,000.00 Overhead Applied - 150% of DL 105,000.00 45,000.00 Answer c. Product 1 Product 2 Direct Labor 70,000.00 30,000.00 Direct Materials 40,000.00 50,000.00 Overhead 105,000.00 45,000.00 Total Cost 215,000.00 125,000.00 Answer d. Product 1 Product 2 Sales 300,000.00 150,000.00 Total Cost 215,000.00 125,000.00 Gross Profit 85,000.00 25,000.00 No. of Units Sold 7,000.00 3,000.00 Gross Profit per Unit 12.14 8.33 Answer e. Calculation of Overhead Rate Under ABC Method Activity Cost Pool Estimated Overhead Expected use of Cost Drivers Activity-Based Overhead rate Machining 70,000 5,000 Mach. Hrs 14.00 per mach. Hr Setup 50,000 40 setups 1,250.00 per setup Packaging 30,000 10,000 units 3.00 per unit Total 150,000 Answer f. Assigning Overhead Cost to Product Model Using ABC Method Activity Based Overhead Rate Product 1 Product 2 Cost Driver Incurred OH Allocated Cost Driver Incurred OH Allocated Machining 14.00 per mach. Hr 4,000 Mach. Hrs 56,000.00 1,000 Mach. Hrs 14,000.00 Setup 1,250.00 per setup 30 setups 37,500.00 10 setups 12,500.00 Packaging 3.00 per unit 7,000 units 21,000.00 3,000 units 9,000.00 Total 114,500.00 35,500.00 Answer g. Product 1 Product 2 Direct Labor 70,000.00 30,000.00 Direct Materials 40,000.00 50,000.00 Overhead 114,500.00 35,500.00 Total Cost 224,500.00 115,500.00 Answer h. Product 1 Product 2 Sales 300,000.00 150,000.00 Total Cost 224,500.00 115,500.00 Gross Profit 75,500.00 34,500.00 No. of Units Sold 7,000.00 3,000.00 Gross Profit per Unit 10.79 11.50
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.