At the end of the year, the company assembled the following actual cost data rel
ID: 2346512 • Letter: A
Question
At the end of the year, the company assembled the following actual cost data relating to all jobs worked on during the year: Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used. (Round your answer to 2 decimal places. Input all amounts as positive values. Omit the "$" sign in your response.) Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used. (Input all amounts as positive values. Omit the "$" sign in your response.)Explanation / Answer
1.Compute the underapplied or overapplied overhead for the year, assuming that a plantwide overhead rate is used.
Plantwide overhead rate = $1,443,010 / 901,000 = $1.60
Manufacturing overhead applied 901,000 x $1.70 $1,443,010
Actual manufacturing overhead $1,484,000
Under applied $40,900
2.Compute the underapplied or overapplied overhead for the year, assuming that departmental overhead rates are used.
Fabricating Machining Assembly Total
Manuf.OH applied $537,000 $806,010 100,000 $1,443,010
Actual $561,000 $830,000 $93,000 $1,484,000
Under applied $24,000 $23,990 $40,990
Over applied $7,000