Direct Labor Variances Alpine Bicycle Company manufactures road bikes. The follo

ID: 2379755 • Letter: D

Question

Direct Labor Variances

Alpine Bicycle Company manufactures road bikes. The following data for September of the current year are available:

a.  Determine the direct labor rate variance and direct labor time variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

b.  How much direct labor should be debited to Work in Process?
$

Direct Labor Variances

Alpine Bicycle Company manufactures road bikes. The following data for September of the current year are available:

Quantity of direct labor used 480 hrs. Actual rate for direct labor $11.30 per hr. Bicycles completed in September 230 Standard direct labor per bicycle 2 hrs. Standard rate for direct labor $11.50 per hr.

a.  Determine the direct labor rate variance and direct labor time variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.

Rate variance $ Time variance $ Total direct labor cost variance $

b.  How much direct labor should be debited to Work in Process?
$


Explanation / Answer

Hi,


Please find the answer as follows:


Standard Production with 480 hours should been = 480/2 = 240 bicycles


Actual Units Completed with 480 hours was = 230 bicycles


Work in Process (Units) at the end of the month = 240 - 230 = 10 bicycles


Amount of direct labor debited to Work in Process = 10*11.50 = 115


Answer is 115.


Thanks.