two departments, and actual information for one of its products, Product 1:
1. Using a plantwide allocation system with machine hours as the cost driver, what was the allocation to Product 1 [round overhead rates to the nearest cent]?
Please help me. This is the only problem I can't get.
Explanation / Answer
Statement showing computations Particulars Amount Overhead in Deptt X 6,800,000.00 Overhead in Deptt Y 2,100,000.00 Total Overhead 8,900,000.00 Machine hours in Deptt X 110,000.00 Machine hours in Deptt Y 120,000.00 Total Machine hours 230,000.00 Plant Wide Overhead Rate = 8,900,000/230,000 38.70 Calculation of Overhead Allocated to Product1 Overhead in Deptt X = 1100 *38.70 42,570.00 Overhead in Deptt Y = 890 *38.70 34,443.00 Total Overhead to Product 1 77,013.00