Job Order Cost Sheet Carlin Furniture Company refinishes and reupholsters furnit

ID: 2424992 • Letter: J

Question

Job Order Cost Sheet

Carlin Furniture Company refinishes and reupholsters furniture. Carlin Furniture uses a job order cost system. When a prospective customer asks for a price quote on a job, the estimated cost data are inserted on an unnumbered job cost sheet. If the offer is accepted, a number is assigned to the job, and the costs incurred are recorded in the usual manner on the job cost sheet. After the job is completed, reasons for the variances between the estimated and actual costs are noted on the sheet. The data are then available to management in evaluating the efficiency of operations and in preparing quotes on future jobs. On July 6, 2014, an estimate of $3,430 for reupholstering a sofa and loveseat was given to Justin Flannigan. The estimate was based on the following data:

On July 10, the sofa and loveseat were picked up from the residence of Justin Flannigan, 310 Suzuki Drive, Lubbock, TX, with a commitment to return it on September 7. The job was completed on September 3.

The related materials requisitions and time tickets are summarized as follows:

Required:

Enter amounts as positive numbers.

1. Complete that portion of the job order cost sheet that would be prepared when the estimate is given to the customer.

2. Record the costs incurred, and complete the job order cost sheet.

What is the best explanation for the variances between actual costs and estimated costs. (For this purpose, assume that three meters of materials were spoiled, the factory overhead rate has been proved to be satisfactory, and an inexperienced employee performed the work.)

Select the correct answer from the above choices.

Estimated direct materials: 40 meters at $35 per meter $ 1,400 Estimated direct labor: 20 hours at $30 per hour 600 Estimated factory overhead (75% of direct labor cost) 450 Total estimated costs $2,450 Markup (40% of production costs) 980 Total estimate $3,430

Explanation / Answer

Solution:


1) and 2)

JOB ORDER COST SHEET

Customer

Justin Flannigan

Date

July 6, 2014

Address

310 Suzuki Drive

Date wanted

Sept. 7, 2014

Lubbock, TX

Date completed

Sept. 3, 2014

Item

Reupholster Sofa and Loveseat

Job. No.

ESTIMATE

Direct Materials

Direct Labor

Summary

Amount

Amount

Amount

40 Meters at $35

1,400

20 Hours at $30

600

Direct Materials

$1,400

Direct Labor

$600

Factory Overhead

$450

Total

1,400

Total

600

Total cost

$2,450

ACTUAL

Direct Materials

Direct Labor

Summary

Mat. Req. No.

Description

Amount

Time Ticket No.

Description

Amount

Item

Amount

310

20 Meters at $35

$700

H50

10 Hours at $30

$300

Direct Materials

$1,540

Direct Labor

$720

312

24 Meters at $35

$840

H55

14 Hours at $30

$420

Factory Overhead

$540

Total

$1,540

Total

$720

Total Cost

$2,800

Actual factory overhead is 75% of direct labor cost. Therefore, 75% x $720 = $540.

The direct materials cost exceeded the estimate by $140 because 4 meters of materials were spoiled. The direct labor cost exceeded the estimate by $120 because an additional 4 hours of labor were used by an inefficient employee. Hence, the direct materials cost exceeded the estimate because materials were spoiled and the direct labor cost exceeded the estimate because additional hours of labor were used by an inexperienced employee

JOB ORDER COST SHEET

Customer

Justin Flannigan

Date

July 6, 2014

Address

310 Suzuki Drive

Date wanted

Sept. 7, 2014

Lubbock, TX

Date completed

Sept. 3, 2014

Item

Reupholster Sofa and Loveseat

Job. No.

ESTIMATE

Direct Materials

Direct Labor

Summary

Amount

Amount

Amount

40 Meters at $35

1,400

20 Hours at $30

600

Direct Materials

$1,400

Direct Labor

$600

Factory Overhead

$450

Total

1,400

Total

600

Total cost

$2,450

ACTUAL

Direct Materials

Direct Labor

Summary

Mat. Req. No.

Description

Amount

Time Ticket No.

Description

Amount

Item

Amount

310

20 Meters at $35

$700

H50

10 Hours at $30

$300

Direct Materials

$1,540

Direct Labor

$720

312

24 Meters at $35

$840

H55

14 Hours at $30

$420

Factory Overhead

$540

Total

$1,540

Total

$720

Total Cost

$2,800