Direct Labor Variances La Batre Bicycle Company manufactures commuter bicycles f
ID: 2432983 • Letter: D
Question
Direct Labor Variances
La Batre Bicycle Company manufactures commuter bicycles from recycled materials. The following data for July of the current year are available:
a. Determine the direct labor rate variance, direct labor time variance, and total direct labor cost variance. Enter a favorable variance as a negative number using a minus sign and an unfavorable variance as a positive number.
b. How much direct labor should be debited to Work in Process?
$
Explanation / Answer
a) Direct labour rate variance = (11.7-11.50)*600 = -120 F
Direct labour efficiency variance = (280*2-600)*11.70 = 468 U
Total direct labour cost variance = (280*2*11.70-600*11.50) = 348 U
b) Direct labour should be debited in work in process = 280*2*11.70 = $6552