Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Question 29 Lewis Company budgeted variable overhead for the year is $120,000. E

ID: 2441814 • Letter: Q

Question

Question 29

Lewis Company budgeted variable overhead for the year is $120,000. Expected activity is 20,000 standard direct labor hours. The actual hours worked were 18,000 and the standard hours allowed for actual production were 19,500. The variable overhead efficiency variance is:

Answer

$0.

$12,000 F.

$3,000 F.

$9,000 F.

none of these.

Question 30

Figure 10-4.
Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:

Units produced: 280,000
Direct labor: 570,000 hours @ $9
Variable overhead: $2,320,000
Fixed overhead: $872,000

Refer to Figure 10-4. The predetermined fixed overhead rate is:

Answer

$3 per direct labor hour.

$1.50 per direct labor hour.

$5.50 per direct labor hour.

$4 per direct labor hour.

none of these.

Question 31

Figure 10-4.
Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:

Units produced: 280,000
Direct labor: 570,000 hours @ $9
Variable overhead: $2,320,000
Fixed overhead: $872,000

Refer to Figure 10-4. The predetermined variable overhead rate is:

Answer

$3.00 per direct labor hour.

$1.50 per direct labor hour.

$5.50 per direct labor hour.

$4.00 per direct labor hour.

none of these.

Question 32

Figure 10-4.
Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:

Units produced: 280,000
Direct labor: 570,000 hours @ $9
Variable overhead: $2,320,000
Fixed overhead: $872,000

Refer to Figure 10-4. Calculate the applied fixed overhead.

Answer

$840,000

$855,000

$864,000

$910,000

none of these

Question 33

Figure 10-4.
Lewis Company calculates its predetermined rates using practical volume, which is 288,000 units. The standard cost system allows 2 direct labor hours per unit produced. Overhead is applied using direct labor hours. The total budgeted overhead is $3,168,000, of which $864,000 is fixed overhead. The actual results for the year are as follows:

Units produced: 280,000
Direct labor: 570,000 hours @ $9
Variable overhead: $2,320,000
Fixed overhead: $872,000

Refer to Figure 10-4. Calculate the fixed overhead spending variance.

Answer

$32,000 F

$0

$8,000 U

$32,000 U

$8,000 F

Lewis Company budgeted variable overhead for the year is $120,000. Expected activity is 20,000 standard direct labor hours. The actual hours worked were 18,000 and the standard hours allowed for actual production were 19,500. The variable overhead efficiency variance is:

Answer

$0.

$12,000 F.

$3,000 F.

$9,000 F.

none of these.

Explanation / Answer

29. (19,500-18,000)* $6= $9,000 F 30. 864,000/288,000*2= $1.50 per hour 31. 2,304,000/288,000*2= $4.00 per hour 32. 570,000* $1.50= $855,000. 33. 872,000-(280,000*2*1.50)= 32,000U

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote