Jaster Corporation\'s management keeps track of the time it takes to process ord

ID: 2462975 • Letter: J

Question

Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order: Compute the throughput time.(Round your answer to 2 decimal places.) Compute the manufacturing cycle efficiency (MCE) (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the sign in your response.) What percentage of the production time is spent in non-vakie-added activities? (Do not round Intormodiato calculations. Round your answer to nearest whole percentage. Omit the sign in your response.) Compute the delivery cycle time (Round your answer to 1 decimal place.)

Explanation / Answer

a. Throughput time is total of Process time, Inspection time, move time adn queue time. ,so = 3.60 + 0.30 + 2.50 + 3.30 = 9.70 days

b. Manufacturing Cycle efficiency = Process time / (total of wait + inspection + move + queue time)

=3.60 / (11.80 + 0.30 + 2.5 + 3.3) = 20.11%

c. The production time is spent in non-value-added activities: Non value added activities includes wait , inspection, move and queue time. So, the time spent in Non value added activities are: 11.80 + 0.30 + 2.5 + 3.3 = 17.90 days

d. The delivery cycle time = It is process, wait , inspection, move and queue time. So, 3.60 + 11.80 + 0.30 + 2.5 + 3.3 = 21.50 days