What is the total cost to be accounted for?What is the amount of conversion cost
ID: 2473616 • Letter: W
Question
What is the total cost to be accounted for?What is the amount of conversion cost transferred to finished goods?What is the cost of ending work in process inventory for conversion?
What is the cost per equivalent unit for conversion?[The following information applies to the questions displayed below.]
What is the cost of materials transferred to finished goods?
What is the cost of ending work in process inventory for materials?
Clopack Company manufactures one product that goes through one processing department called Mixing. All raw materials are introduced at the start of work in the Mixing Department. The company uses the weighted-average method to account for units and costs. Its Work in Process T-account for the Mixing Department for June follows (all forthcoming questions pertain to June):
The June 1 work in process inventory consisted of 4,600 pounds with $15,000 in materials cost and $13,000 in conversion cost. The June 1 work in process inventory was 100% complete with respect to materials and 60% complete with respect to conversion. During June, 37,100 pounds were started into production. The June 30 work in process inventory consisted of 8,400 pounds that were 100% complete with respect to materials and 50% complete with respect to conversion.
What is the total cost to be accounted for?What is the amount of conversion cost transferred to finished goods?What is the cost of ending work in process inventory for conversion?
What is the cost per equivalent unit for conversion?[The following information applies to the questions displayed below.]
What is the cost of materials transferred to finished goods?
What is the cost of ending work in process inventory for materials?
Explanation / Answer
COMPLETED UNITS = OPENNING INVENTORY + INTRODUCED - ENDING INVENTORY
= 4600 + 37100 - 8400
= 33300
COMPUTATION OF EQUIVALENT UNITS
MATERIAL CONVERSION
COMPLETED 33300 33300
(+)ENDING WIP 8400 4200
TOTAL 41700 37500
COST PER UNIT 147630+15000 / 41700 93500+111000+13000 / 37500
= $3.9 $5.8
Cost of materials transferred to finished goods = 33300 * 3.9
= $129870
Cost of ending work in process inventory for materials = 8400 * 3.9
= $ 32760
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.