Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:
Compute the throughput time.(Round your answer to 2 decimal places.)
Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)
What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)
Compute the delivery cycle time. (Round your answer to 1 decimal place.)
Explanation / Answer
( a ) Through put time
(b) Manufacturing cycle efficiency(MCE)
MCE = Value added time / throughput time = 3.25 / 7.85 =0.414
where,
Value added time = process time =3.25
(c) Percentage of production time spent in non value activities(%) = 100% -MCE(%) = 100- 41.4% =58.6%
(d) Delivery cycle time = wait time + throughput time = 11.4 +7.85 =19.25 days
Process time 3.25 Add:Inspection time 0.3 Add:Move time 1.2 Add:Queue time 3.1 Throughput time 7.85Related Questions