Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:
Compute the throughput time.(Round your answer to 2 decimal places.)
Compute the manufacturing cycle efficiency (MCE). (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)
What percentage of the production time is spent in non-value-added activities? (Do not round intermediate calculations. Round your answer to nearest whole percentage. Omit the "%" sign in your response.)
Compute the delivery cycle time. (Round your answer to 1 decimal place.)
Jaster Corporation's management keeps track of the time it takes to process orders. During the most recent month, the following average times were recorded per order:
Explanation / Answer
(a)Throughput time Inspection Time 0.6 Process Time 1.95 Move Time 1.7 Queue Time 3.1 7.35 (b)Manufacturing Cycle Efficiency MCE = Value-added time / Throughput time Only process time (2.0 days) represents value-added time MCE 26.53061224 ©Percentage of the production time is spent in non-value-added activities Wait Time 16.7 Inspection Time 0.6 Process Time 1.95 Move Time 1.7 Queue Time 3.1 24.05 Non value added Activities Time 22.1 Percentage of the production time is spent in non-value-added activities 91.89189189 (D)Delivery cycle time Wait Time 16.7 Inspection Time 0.6 Process Time 1.95 Move Time 1.7 Queue Time 3.1 24.05