Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Hello, I have a probelm here and I also have the model solutions, but I have tro

ID: 2493592 • Letter: H

Question

Hello, I have a probelm here and I also have the model solutions, but I have trouble understanding point 3, I don't know where the numbers are coming from. If anybody could explain please, it will be great. Thanks a lot for your help.

Please find below the problem

Kitchen King’s Singapore plant manufactures three product lines, all multi-burner ceramic

cooktops. The plant’s three product models are the Regular (REG), the Advanced (ADV)

and the Gourmet (GMT). Until recently, the plant used a job costing system, with

manufacturing overhead applied on the basis of direct labour hours. The following table

displays the basic data upon which the conventional costing system was based.

Planned annual production

REG

ADV

GMT

Volume in units

5000

4000

1000

Production runs

40 runs of 125 units

40 runs of 100 units

20 runs of 50 units

Direct material

$129

$151

$203

Direct labour (not including setup)

$171 (9 hrs @ $19

per hr)

$209 (11 hrs @ $19

per hr)

$247 (13 hrs @ $19

per hr)

Machine hours (MH) per product unit

10 MH

12 MH

17 MH

Total machine hours consumed by product

line in a year

50 000 (10 MH ×

5000)

48 000 (12 MH ×

4000)

17 000 (17 MH ×

1000)

The annual budgeted overhead is $1 224 000 and the company’s predetermined

overhead rate is $12 per direct labour hour. The product costs for the three product

models, as reported under the plant’s traditional costing system, are shown in the

following table:

REG

ADV

GMT

Direct material

$129

$151

$203

Direct labour (not including setup

time)

$171

$209

$247

Manufacturing overhead

$108 (9 hrs @ $12

per hr)

$132 (11 hrs @ $12

per hr)

$156 (13 hrs @ $12

per hr)

Total

$408

$492

$606

Kitchen King’s pricing policy is to set a target price for each product equal to 130 per

cent of the full product cost. Due to price competition from other appliance manufacturers,

REG units were selling at $525 and ADV units were selling for $628. These prices were

somewhat below the firm’s target prices. However, these results were partially offset by

great-than-expected profits on the GMT product line. Management had raised the price on

the GMT model to $800 which was higher than the original target price. Even at this price,

Kitchen King’s customers did not seem to hesitate to place orders. Moreover, the

company’s competitors did not mount a challenge in the market for the GMT product line.

Nevertheless, concern continued to mount in Singapore about the difficulty in the REG and

ADV markets. After all, these were the plant’s bread-and-butter products, with projected

annual sales of 5000 REG units and 4000 ADV units.

Kitchen King’s director of cost management, Angela Hui, had been thinking for some

time about a refinement in the Singapore plant’s product costing system. Hui wondered if

the conventional volume-based system was providing management with accurate data

about product costs. She had read about activity-based costing and wondered if ABC

would be an improvement to the plant’s product costing system. After some discussion, an

ABC proposal was made to the company’s top management and approval was obtained.

The data collected for the new ABC system is displayed in the following table.

Activity

Activity cost

Activity driver

Product line

Quantity of activity driver

Machine related

$310 500

Machine hours

REG

ADV

GMT

Total

50 000

48 000

17 000

115 000

Material handling

52.500

Production runs

REG

ADV

GMT

Total

40

40

20

100

Purchasing

75 000

Purchase orders

REG

ADV

GMT

Total

1.0

96

104

300

Setup

85 000

Production runs

REG

ADV

GMT

Total

40

40

20

100

Inspection

27.500

Inspection hours

REG

ADV

GMT

Total

4.0

4.0

300

1 100

Shipping

66 000

Shipments

REG

ADV

GMT

Total

5.0

4.0

200

1 100

Engineering

32.500

Engineering hours

REG

ADV

GMT

Total

250

2.0

200

650

Facility

575 000

Machine hours

REG

ADV

GMT

Total

50 000

48 000

17 000

115 000

Required:

1. Show how the company’s overhead rate of $12 per direct labour hour was

calculated.

2. Complete an activity-based costing analysis for Kitchen King’s three product lines.

3. Prepare a table which estimates the new product cost for each product line under ABC.

Planned annual production

REG

ADV

GMT

Volume in units

5000

4000

1000

Production runs

40 runs of 125 units

40 runs of 100 units

20 runs of 50 units

Direct material

$129

$151

$203

Direct labour (not including setup)

$171 (9 hrs @ $19

per hr)

$209 (11 hrs @ $19

per hr)

$247 (13 hrs @ $19

per hr)

Machine hours (MH) per product unit

10 MH

12 MH

17 MH

Total machine hours consumed by product

line in a year

50 000 (10 MH ×

5000)

48 000 (12 MH ×

4000)

17 000 (17 MH ×

1000)

Explanation / Answer

Answer 1 Calculation of Company's overhead rate of $12 per direct labour hour Product REG ADV GMT Total Volume in units 5000 4000 1000 Direct labour per unit 9 11 13 Total Direct Labour hours 45000 44000 13000 102000 Annual Budgeted overhead = $1224000 Predetermined Overhead rate = Annual Budgeted overhead / Total Direct Labour hours = $1224000 / 102000 hours = $12 per direct labour hour Answer 2 Calculation of activity rate Activity Activity Cost Total Quantity of activity driver Activity Rate Activity Driver A B A / B Machine related $3,10,500.00 115000 $2.70 per machine hour Material handling $52,500.00 100 $525.00 per production run Purchasing $75,000.00 300 $250.00 per purchase order Setup $85,000.00 100 $850.00 per production run Inspection $27,500.00 1100 $25.00 per inspection hour Shipping $66,000.00 1100 $60.00 per shipment Engineering $32,500.00 650 $50.00 per engineering hour Facility $5,75,000.00 115000 $5.00 per machine hour Allocation of overhead cost based on activity rate Product REG ADV GMT Total Machine related $1,35,000.00 $1,29,600.00 $45,900.00 $3,10,500.00 Material handling $21,000.00 $21,000.00 $10,500.00 $52,500.00 Purchasing $25,000.00 $24,000.00 $26,000.00 $75,000.00 Setup $34,000.00 $34,000.00 $17,000.00 $85,000.00 Inspection $10,000.00 $10,000.00 $7,500.00 $27,500.00 Shipping $30,000.00 $24,000.00 $12,000.00 $66,000.00 Engineering $12,500.00 $10,000.00 $10,000.00 $32,500.00 Facility $2,50,000.00 $2,40,000.00 $85,000.00 $5,75,000.00 Total $5,17,500.00 $4,92,600.00 $2,13,900.00 $12,24,000.00 Answer 3 Calculation of new product cost for each product Line under ABC Product REG ADV GMT Volume in units 5000 4000 1000 Direct Material $6,45,000.00 $6,04,000.00 $2,03,000.00 Direct Labour $8,55,000.00 $8,36,000.00 $2,47,000.00 Overhead based on ABC $5,17,500.00 $4,92,600.00 $2,13,900.00 Total Cost $20,17,500.00 $19,32,600.00 $6,63,900.00 Cost per unit $403.50 $483.15 $663.90

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote